Move a hosted server to another project
Last update:

Move a hosted server to another project

Users with the Account Administrator, Account Owner and Project Administrator roles can move the server to another project. A user with the Project Administrator role must be added as an administrator for these projects.

Move one server

  1. In the control panel, from the top menu, click ProductsHardware Placement.
  2. From the server menu, select Transfer to another project.
  3. Select the project to which you want to move the server.
  4. Click Transfer.

Migrate multiple servers

  1. In the control panel, from the top menu, click ProductsHardware Placement.
  2. Click Transfer to another project.
  3. Select the servers you want to migrate.
  4. Select the project to which you want to migrate the servers.
  5. Click Transfer.