Modify the rack for a dedicated server
Any ordered server will be located in a rack in the server room. For more details, see the Pool section of the Locations instructions.
Ready-to-use servers, including Chipcore, are installed in racks in advance. Custom configuration servers are installed in available rack spaces after they are ordered. When ordering multiple servers, our algorithm analyzes technical capabilities at the time of the order and attempts to place the servers in different racks to increase fault tolerance.
Each rack has three points of failure: an internet port, a local port, and power. In extremely rare cases, rack performance may be disrupted. If service downtime of even a few minutes is critical, we recommend placing your servers so that servers of the same project are located in different racks. This will minimize the risk of service unavailability during a rack failure.
You can view current server locations and submit a request to move a server to a different rack in the Control panel: in the top menu, click Products and select Dedicated Servers → Servers → the Rack location **** tab.
Move a server to a different rack
You can move a server between racks only within the same pool.
- In the Control panel, on the top menu, click Products and select Dedicated Servers.
- In the Servers section, open the Rack location **** tab.
- Select the rack from which you need to move the server and click Request server migration.
- Select the server(s) to migrate.
- In the Comment field, enter additional information, for example, specify racks that the server should not be moved to, or servers that you cannot share a rack with.
- Click Request relocation. A ticket with the server relocation request will be automatically created.
- Wait for a Selectel employee to respond regarding the feasibility of relocating your server. If server relocation is possible, the employee will confirm a convenient time for the work and will notify you when the work is complete after the server has been moved to a different rack.